Application Prerequisites
When remodeling your basement a permit is required. You will also need two sets of drawings showing the following:
- Wall Construction, including lumber, spacing, drywall, etc.
- Layout of basement showing location of partitions, furnace, windows, etc.
- Identification of all rooms including bedrooms, office, laundry room, etc.
- Electrical layout for all outlets, lighting, etc.
- Bathroom layout and venting, if applicable
For additional information on construction requirements please see the basement remodel requirement information.
Applications
Inspections Required
- A rough inspection is required before drywall is installed.
- Final inspections are required when the work is complete.
- Please submit an inspection request before 4:00 p.m. the previous work day prior to the date you are requesting the inspection for.
- Inspection requests are not taken over the phone.